Multiple digesters at a large midwestern plant, roughly 500 miles from the Somerset yard. At that distance there is no local depot to fall back on. Everything that rolls in has to keep running for the duration.
The site photograph shows the spread on arrival: an MSS mixing tank with integrated access platform and railing, suction lines run out, and one of our own tractors alongside. Full drawdown, on-site dewatering, confined-space cleaning and disposal followed, with generators on site for power.
173 days on site, September 2023 through to the following spring: one crew, one schedule, and the same equipment on the pad from the first day to the last.
This job ran under Digester cleaning. Working a vessel like this one? Send us dimensions and rough volume and we will tell you what the job takes.